From zoning application to certificate of occupancy.

Where zoning permits go: refused or not, whether the ZBA hears an appeal, and how many reach a building permit and a certificate of occupancy.

MeasureUnits are known only for appealed permits.
Cohort: year appliedBuilding-permit links barely exist before 2020.
Permit typeChange-of-use permits never need a building permit.
Pipeline activity (hop tiles)

Flow: where a group of permits ended up

Permits applied for since 2021, new construction and additions only, council district 2.

311
Appealed permits
83%
…with a unit count
1,200
Units in those projects
99
Units where a C.O. is recorded

These are units in the projects at each step, as the permit or appeal describes them. They are not net new homes: a duplex conversion counts as two. Only appealed permits are shown, because the unit count comes from the appeal and is missing for most other zoning permits. A few large projects hold a big share of the units, so read the permit count beside each total.

ZONING PATHPERMITBUILDING PERMITCERTIFICATE OF OCCUPANCYAppealed: granted → Zoning permit issued: 880Appealed: granted → Not issued (denied, expired or cancelled): 19Appealed: denied → Zoning permit issued: 1Appealed: denied → Not issued (denied, expired or cancelled): 100Appealed: withdrawn or dismissed → Zoning permit issued: 14Appealed: withdrawn or dismissed → Not issued (denied, expired or cancelled): 160Appealed: awaiting decision → Not issued (denied, expired or cancelled): 26Zoning permit issued → Building permit (confirmed): 194Zoning permit issued → Building permit (inferred): 89Zoning permit issued → No linked record: 612Building permit (confirmed) → C.O. recorded: 65Building permit (confirmed) → No C.O. recorded yet: 129Building permit (inferred) → C.O. recorded: 34Building permit (inferred) → No C.O. recorded yet: 55Appealed: granted899 units (75%) · 205 permitsAppealed: denied101 units (8%) · 16 permitsAppealed: withdrawn or dismissed174 units (14%) · 22 permitsAppealed: awaiting decision26 units (2%) · 16 permitsZoning permit issued895 units (75%) · 196 permitsNot issued (denied, expired or cancelled)305 units (25%) · 63 permitsBuilding permit (confirmed)194 units (16%) · 112 permitsBuilding permit (inferred)89 units (7%) · 19 permitsNo linked record612 units (51%) · 65 permitsC.O. recorded99 units (8%) · 48 permitsNo C.O. recorded yet184 units (15%) · 83 permits
Units in projects at each step
Appealed: granted899 units, 205 permits
Appealed: denied101 units, 16 permits
Appealed: withdrawn or dismissed174 units, 22 permits
Appealed: awaiting decision26 units, 16 permits
Zoning permit issued895 units, 196 permits
Not issued (denied, expired or cancelled)305 units, 63 permits
Building permit (confirmed)194 units, 112 permits
Building permit (inferred)89 units, 19 permits
No linked record612 units, 65 permits
C.O. recorded99 units, 48 permits
No C.O. recorded yet184 units, 83 permits

Every start year is drawn to the same scale as the 2020-on group, so a later start year draws a shorter chart.

Census: where housing projects with an appeal sit now

Housing projects (mixed use included) with a ZBA appeal on record and activity in the last 5 years, council district 2, counted at the furthest hop they have reached. This is a snapshot, not a share of the group above, so don't read it as attrition.

Projects at: Stalled

Most recent 40 of 57
  • 1208 S 27TH ST
    2 units · District 2 · last activity 2026-09-15
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 741 S CLEVELAND ST
    1 unit · District 2 · last activity 2025-12-19
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1408-10 REED ST
    6 units · District 2 · last activity 2025-11-20
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: reached
    4. Construction: reached
    5. C.O.: no record
  • 1541 S DOVER ST
    1 unit · District 2 · last activity 2025-11-19
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: reached
    4. Construction: reached
    5. C.O.: no record
  • 2324 WAVERLY ST
    1 unit · District 2 · last activity 2025-11-18
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1944 WILDER ST
    1 unit · District 2 · last activity 2025-10-28
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: reached
    4. Construction: reached
    5. C.O.: no record
  • 2029 S 20TH ST
    3 units · District 2 · last activity 2025-10-07
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: reached
    4. Construction: reached
    5. C.O.: no record
  • 1225 CONSTITUTION AVE
    346 units · District 2 · last activity 2025-10-06
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: reached
    4. Construction: reached
    5. C.O.: no record
  • 1618 WEBSTER ST
    District 2 · last activity 2025-09-25
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1163 S 19TH ST
    2 units · District 2 · last activity 2025-09-24
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 2838 CANTRELL ST
    1 unit · District 2 · last activity 2025-08-26
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 2614 PINE ST
    1 unit · District 2 · last activity 2025-07-30
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1600 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1602 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1604 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1606 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1608 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1610 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1612 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1614 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1616 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1618 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1620 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1622 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1624 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1626 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1628 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1630 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1632 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1634 S DOVER ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1631 S 29TH ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1633 S 29TH ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1635 S 29TH ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1637 S 29TH ST
    1 unit · District 2 · last activity 2025-06-27
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 2649 S 18TH ST
    1 unit · District 2 · last activity 2025-04-28
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 2717 FEDERAL ST
    3 units · District 2 · last activity 2025-04-28
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1222 S HARMONY ST
    1 unit · District 2 · last activity 2025-03-24
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 2500 FEDERAL ST
    2 units · District 2 · last activity 2025-03-14
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 735 S 10TH ST
    1 unit · District 2 · last activity 2025-01-11
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record
  • 1627 RITNER ST
    1 unit · District 2 · last activity 2024-11-25
    1. Zoning: reached
    2. Appeal: reached
    3. Building permit: no record
    4. Construction: no record
    5. C.O.: no record

Filled dot: reached. Open ring: no record found, which is not the same as a project failing.

How we read these numbers

  • Confirmed building permits name the zoning permit's job directly. Inferred ones are a later new-construction permit on the same parcel. No linked record means we found neither. It does not mean the project failed.
  • Appeals are matched to the permit they contest. Permits are counted once, even when recorded on more than one parcel.
  • Cohorts start in 2020 because links from zoning permits to building permits barely exist before then.
  • Counts by council district use the appeal's district where there is one, otherwise the parcel's.

ZBA Watch tracks the Zoning Board of Adjustment because housing supply is Build Philly Now's subject — choosing to measure wait times, unit counts, and case volume is itself a point of view. Cases are scoped to appeal numbers starting "ZP-", 2020–present; earlier ZBA cases are planned but not yet loaded. Approvals and denials are rendered the same way — this site aggregates and monitors, it does not score outcomes as good or bad.

Source: City of Philadelphia Department of Licenses & Inspections via CARTO. Data updates periodically and may not reflect the most recent hearings or decisions.

Permit Pipeline | ZBA Watch