From zoning application to certificate of occupancy.
Where zoning permits go: refused or not, whether the ZBA hears an appeal, and how many reach a building permit and a certificate of occupancy.
Flow: where a group of permits ended up
Permits applied for since 2021, all types, council district 10.
1,471
Zoning permit applications
20%
Refused at first review
262
Appealed to the ZBA
75%
Appeals granted (of decided)
56%
Issued permits with a confirmed or inferred building permit
| By right | 1182 |
|---|---|
| Refused, no appeal found | 27 |
| Appealed: granted | 174 |
| Appealed: denied | 24 |
| Appealed: withdrawn or dismissed | 34 |
| Appealed: awaiting decision | 30 |
| Zoning permit issued | 1328 |
| Not issued (denied, expired or cancelled) | 143 |
| Building permit (confirmed) | 710 |
| Building permit (inferred) | 29 |
| No linked record | 589 |
| C.O. recorded | 154 |
| No C.O. recorded yet | 585 |
Every start year is drawn to the same scale as the 2020-on group, so a later start year draws a shorter chart.
Census: where housing projects with an appeal sit now
Housing projects (mixed use included) with a ZBA appeal on record and activity in the last 24 months, council district 10, counted at the furthest hop they have reached. This is a snapshot, not a share of the group above, so don't read it as attrition.
Projects at: Stalled
1 projects- 834 AVON RD1 unit · District 10 · last activity 2026-04-27
- Zoning: reached
- Appeal: reached
- Building permit: no record
- Construction: no record
- C.O.: no record
Filled dot: reached. Open ring: no record found, which is not the same as a project failing.
How we read these numbers
- Confirmed building permits name the zoning permit's job directly. Inferred ones are a later new-construction permit on the same parcel. No linked record means we found neither. It does not mean the project failed.
- Appeals are matched to the permit they contest. Permits are counted once, even when recorded on more than one parcel.
- Cohorts start in 2020 because links from zoning permits to building permits barely exist before then.
- Counts by council district use the appeal's district where there is one, otherwise the parcel's.